Keep the application and design review moving together
The City of Miami uses iBuild to manage building applications and ProjectDox for digital plan review. Public Works applications use iPW. [S1]
One development can leave the owner with several conversations to follow. We coordinate the applicable records around the same building scope, identify the review that needs a response and bring in the designer responsible for it. You get a person working the outstanding issue instead of spending your time translating portal updates into instructions for the project team.
Make the next review cycle count
Miami’s commercial expedited-review program requires the project to complete an initial plan-review cycle before a request can proceed. [S2]
That makes the response to the first comments important. We work with the architect and engineers to separate a clarification from a design revision, negotiate the substance of the comment and prepare a coordinated response. When an expedited path fits the project, we pursue it with the unresolved technical questions already assigned to the people who can answer them.
Choose review support around the actual obstacle
Miami offers after-hours expedited review for qualifying commercial projects across multiple disciplines; fire expedited review has a separate request route. [S2]
We assess the available program against the building’s scope and the review holding up construction. An expedited review is useful when the right technical professionals are ready for it. Commercial Permits coordinates that preparation and follows the resulting comments, so the owner is not left arranging an appointment and then managing the design response alone.
Account for site constraints beyond the building drawings
Miami’s building guidance identifies historic-property rules and, where excavation affects an archaeological conservation area, a Certificate to Dig. [S1]
We investigate whether those issues affect your proposed development and connect the answer to the permit effort. If an additional review is relevant, our team coordinates the city discussion with your architect and site professionals. The goal is to expose the actual constraint early enough for your designers to address it, with one person following the answer through.
Follow the building to the correct closeout
Miami distinguishes a Certificate of Occupancy for new construction or change of use from a Certificate of Completion for remodels, renovations and shell buildings. [S3]
We keep the planned building outcome in view throughout the permit work. A shell delivery and an occupied facility call for different closeout conversations. Commercial Permits works with the contractor and design team on the outstanding items, brings forward the decisions that need your input and follows the remaining approval instead of treating plan acceptance as the finish line.
Resolve the items still standing between completion and opening
Before issuing a CO or CC, Miami requires the permit to be final, outstanding revisions or requests completed, and final inspections approved. [S3]
Our white-glove team follows those dependencies with the responsible project parties. You provide the plans and introduce us to your architect and engineers; we manage the daily city contact, comment coordination and resubmittals. Get started or Talk to A Permitting Expert about the complete commercial building you want to move forward in the City of Miami.
How Commercial Permits helps your project
How can Commercial Permits help my ground-up project get to construction faster?
Commercial Permits puts a dedicated permit expert in charge of moving your project through review. Our experts work with cities every day: pursuing review priority and available expedited paths, negotiating comments, finding compliant alternatives and challenging avoidable fee assessments. We coordinate directly with your architect of record and engineers to keep answers, revisions and resubmittals moving. You have one team pushing the permitting work forward so you can focus on getting the project built.
How much time do I need to spend on permits if I work with Commercial Permits?
No day-to-day permit management. Give us your plans and connect us with your architect and engineers; Commercial Permits takes it from there. Our white-glove team handles submissions, city follow-up, comment coordination and resubmittals with your design team. We keep you updated and bring you the project decisions that need your input. You do not have to chase reviewers, manage the permit portal or relay comments between the city and your consultants.
Why hire a permitting firm if I can submit online myself?
Submission is step one. The work comes afterward: getting reviews moving, negotiating comments, finding a compliant path through objections and coordinating the responses that get the project to its next decision. A comment can involve the city, your architect and several engineers. Commercial Permits takes ownership of that follow-through, works through the issue with the right people and keeps the response moving. You get experienced judgment and someone accountable for the permit work from submission through closeout.
Put a permit expert to work on your project.
Already working through city comments? See how Commercial Permits handles review comments and resubmittals, and explore a fictional issue tracker, responsibility table and weekly report showing the work our team takes over.
Official sources
- S1 · www.miami.gov — checked 2026-11-02
- S2 · www.miami.gov — checked 2026-11-02
- S3 · www.miami.gov — checked 2026-11-02
City service overview. Availability depends on the property, proposed use and project scope. The reviewing authorities determine requirements and approvals.
Related services for your project
- Miami FBO and Hangar Permits for New Construction and Building Remodels
- Miami commercial building remodel and complete renovation permitting
- Miami car wash new construction and complete facility permitting
- Miami data center new construction and complete facility permitting
- Miami dealership new construction and complete facility permitting
- Miami drone delivery and charging facilities: new construction and complete remodel permitting